Question: Please answer the following multiple choice - You are considering two independent projects both of which have been assigned a discount rate of 12.5 percent.
Please answer the following multiple choice -

You are considering two independent projects both of which have been assigned a discount rate of 12.5 percent. Based on the NPV, what is your recommendation concerning these projects? Time Cash Flow A Cash Flow B 0 -$ 46,500 -$375,000 1 12,200 103,500 2 38,400 105,100 3 11,300 165,000 O Choose Project A since NPV>O and reject Project B since NPV0 Choose both Project A and Project B since they both have NPV>O O It is not possible to make a decision with NPV