Question: Please answer the following question with the complete steps: Scheduling Exercise 1/ Draw the ADA network and identify the critical path. Also calculate the ES,
Please answer the following question with the complete steps:

Scheduling Exercise 1/ Draw the ADA network and identify the critical path. Also calculate the ES, EF, LS, and LF for each activity: Activity Preceding Activity Time (weeks) A - 7 B - 8 C - 6 D A 6 E B 6 F B 8 G C 4 H D, E 7 | F, G, H 3