Question: Please answer the following question with the complete steps: 3/ Draw the network and identify the critical path and associated time. Network Activity Initial Final
Please answer the following question with the complete steps:

3/ Draw the network and identify the critical path and associated time. Network Activity Initial Final Optimistic Pessimistic Most Estimated node node time time likely time A 1 2 1 3 2 B 1 4 4 6 5 C 1 3 4 6 5 D 2 6 2 4 3 E 2 4 1 3 2 F 3 4 2 4 3 G 3 5 7 15 9 H 4 6 4 6 5 I 4 7 6 14 10 J 4 5 1 3 2 K 5 7 2 4 3 L 6 7 6 14 10