Question: Please answer the guide questions below. For the following table of information, Determine the critical path(s) Activity Duration Dependency START 0 days - A 5
Please answer the guide questions below.
For the following table of information, Determine the critical path(s)
| Activity | Duration | Dependency |
| START | 0 days | - |
| A | 5 days | START |
| B | 2 days | START |
| C | 3 days | A,B |
| D | 5 days | START |
| E | 6 days | START |
| F | 4 days | D,E |
| G | 2 days | C,F |
| H | 5 days | G |
| I | 7 days | G |
| J | 3 days | H |
| FINISH | 0 days | I,J |
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Determining the Critical Paths Understanding the Critical Path Before we dive into the calculations lets clarify what a critical path is In project management the critical path is the sequence of acti... View full answer
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock