Question: Please answer the problem in excel format. 3. A production manager has constructed the following (partial) time-phased MPS record Week 1 2 3 4 5

Please answer the problem in excel format.
Please answer the problem in excel format. 3. A
3. A production manager has constructed the following (partial) time-phased MPS record Week 1 2 3 4 5 6 Forecast 203220643564 Orders 243021 Projected Available Balance Available to Promise MPS 92 9292 Lot size = 72. Complete the record. What is the projected available balance at period 6? 92