Question: with excel formulas please 3. A production manager has constructed the following (partial) time-phased MPS record (Chapter 7) Week 1 2 3 3 4 5

with excel formulas please 3. A production

with excel formulas please

3. A production manager has constructed the following (partial) time-phased MPS record (Chapter 7) Week 1 2 3 3 4 5 6 35 5+X u Forecast 20 5+X 20 5+X Orders 24 17 8 Projected Available Balance Available to Promise MPS Lot size = 50+X. Complete the record. What is the projected available balance at period 6? X=35