Question: please answer the question Remaining Time: 2 hours, 44 minutes, 54 seconds. Question Completion Status: QUESTION 11 Long Answer Question Consider the following set of
please answer the question

Remaining Time: 2 hours, 44 minutes, 54 seconds. Question Completion Status: QUESTION 11 Long Answer Question Consider the following set of processes, with the length of the CPU burst has been given in milliseconds. Process Arrival Time CPU Burst P1 0 8 P2 1 2 P3 7 8 Draw the Gantt chart & compute the average waiting and turnaround time for the processes in the above system using Round Robin Scheduling (Time Quantum: 4 ms] Attach File Browse My Computer