Question: please answer the question, thanks Pizza store has a plan to build a new factory to expand their business. Consider the project with the following

please answer the question, thanks
Pizza store has a plan to build a new factory to expand their business. Consider the project with the following dependency matrix and the expected time for each activity. Predecessor Time (weeks) 4 Activity 1 2 3 1 10 2 2 4 Description Needs analysis Architect plans Equipment selection Building permits and zoning Equipment order Construction Interior finish Installation and setup 2 4 5 3 3 6 4,5 16 6 4 7 8 7 1 Find the slack time of the project by drawing an activity network diagram. (20 points)Step by Step Solution