Question: please answer the question within 30 minutes. make sure the answer and reasons are explained in very detailed manner with calculations. answer should not be
please answer the question within 30 minutes. make sure the answer and reasons are explained in very detailed manner with calculations. answer should not be copied from somewhere else i will give negative ratings for sure.

c) The following consideration of risk allowance was made for the Project Risks that remain in the design. Impactjj Likelihood (%) Optimistic outcome 5,189,000.00 (saving) 40 Most likely outcome 18, 160, 000.00 (extra) 50 Pessimistic outcome 7,303,000.00 (extra) 10 i) Provide an estimate for the risk budget. ii) If the cost plan allowance for the project is estimated to be 150 million, calculate the total project cost