Question: Please answer these questions. Please don't copy another answer on this website You're in charge of a project spanning 1 0 0 0 acres of
Please answer these questions. Please don't copy another answer on this website
You're in charge of a project spanning acres of trees, consisting of the activities shown at right.
Use the linear scheduling method to determine how long the project will take if accomplished in the most efficient manner, and depict the diagram to support your determination.
Activity Prod Rate
Cut
Load
Haul
Offload
Stack
What characteristics graphically depict a linear schedule, and what does each represent?
Describe the type of project for which this scheduling method is appropriate, and give examples only one can be from the information presented in class
Identify and describe the other two scheduling methods we've discussed in class. In your description, include the advantage of that scheduling method and include an example of when its use would be most appropriate.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock