Question: Please answer this ASAP..........Q1 and Q 2 EVM Question 1 Calculate Cost variance Task 1 Task 2 Task 3 Task 4 Task 5 Budget Actual


Please answer this ASAP..........Q1 and Q 2
EVM Question 1 Calculate Cost variance Task 1 Task 2 Task 3 Task 4 Task 5 Budget Actual $100 $200 $300 $300 $100 $50 $200 $100 $100 $550 Project status as of this time Earned value (EV) Actual Cost (AC) Cost Variance (CV) 11 11 11 $ $ $ CPI = ? Question 2 Calculate Schedule Variance EVM Budget per task and Schedule as of week 6 Week 6 Week 7 Week 8 Task 1 complete Task 2 complete Task 3 complete Task 4 50% done Task 5 complete Task 6 25% done Task 7 50% done Task 8 75% done Task 9 50% done Task 10 complete Week 1 Week 2 Week 3 Week 4 Week 5 $100 $200 $100 $800 $200 $400 $800 $200 $200 $400 $200 PV = $ EV = $ SV = ? SPI =