Question: EVM Question 1 Calculate Cost variance Task 1 Task 2 Task 3 Task 4 Task 5 Budget Actual $100 $200 $300 $300 $100 $50 $200

EVM Question 1 Calculate Cost variance Task 1

EVM Question 1 Calculate Cost variance Task 1

EVM Question 1 Calculate Cost variance Task 1 Task 2 Task 3 Task 4 Task 5 Budget Actual $100 $200 $300 $300 $100 $50 $200 $100 $100 $550 Project status as of this time Earned value (EV) Actual Cost (AC) Cost Variance (CV) ll || $ $ $ CPI = ? Question 2 Calculate Schedule Variance EVM Budget per task and Schedule as of week 6 Week 6 Week 7 Week 8 Task 1 Task 2 Task 3 Task 4 Task 5 Task 6 Task 7 Task 8 Task 9 Task 10 complete complete complete 50% done complete 25% done 50% done 75% done 50% done complete Week 1 Week 2 Week 3 Week 4 Week 5 $100 $200 $100 $800 $200 $4001 $800 S200S 2001 S400 $200 PV = $ EV = $ SV = ? SPL =

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!