Question: please answer this question Q1: For the project listed below, find the following items: (15 marks) 1- Total project finishing time (3 marks) 2- Critical
please answer this question
Q1: For the project listed below, find the following items: (15 marks) 1- Total project finishing time (3 marks) 2- Critical path (3 marks) 3- Free float for each task. (3marks) 4- If Activity B is delayed by 7 weeks. As a project manager explains how this will affect the total project critical path. (6 marks) Activity Duration in Weeks Dependency or Predecessor Activities B P A U 6 4 3 DEZ 4 2 3 6 C, B, P P A A U R N
Step by Step Solution