Question: please answer me now!! Q1: For the project listed below, find the following items: (15 marks) 3- Free float for each task. (3marks) 4- If

please answer me now!! please answer me now!! Q1: For the project listed
Q1: For the project listed below, find the following items: (15 marks) 3- Free float for each task. (3marks) 4- If Activity B is delayed by 7 weeks. As a project manager explains how this will affect the total project critical path. (6 marks) Activity Duration in Weeks Dependency or Predecessor Activities B P A U R N 6 4 3 7 4 2 3 6 C, B, P P A A U

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!