Question: *Please answer within 25mins* You are fulfilling an order for 45 units for sale at 65 per unit. This involves work in 3 cost centres

*Please answer within 25mins*
You are fulfilling an order for 45 units for sale at 65 per unit. This involves work in 3 cost centres - machining, assembly and finishing. Your company has established the following data: Machining 13 Machine hr OAR per hour Assembly 8 Labour hr OAR per hour Finishing Labour hr OAR 11 per hour Total direct material cost 210 Total machine time 20 hours 50 hrs 6.00 machining per hour 4.50 80 hrs assembly Labour per hour 40 hrs finishing 5.65 per hour OAR for general overheads is 10% of total product cost Using batch costing methods, the unit cost (to the nearest pound sterling ) is: 48 60 39 33Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock