Question: Please answer within 30 min page 1 2 Kerri Lerner wanted to determine her project's SPI. If EV = 42,000, PV = 40,000, and AC
Please answer within 30 min page 1 2
Kerri Lerner wanted to determine her project's SPI. If EV = 42,000, PV = 40,000, and AC = 39,000, what is the SPI?
Select one:
a. 1.16
b. 0.95
c. 1.05
d. 0.98
If EV = 29,000, PV = 30,000, and AC = 25,000, what is the CV?
Select one:
a. -1,000
b. 4,000
c. -4,000
d. 1,000
The goal of a lessons-learned meeting is to recapitulate the series of events:
Select one:
a. As intuitively as possible
b. As subjectively as possible
c. From all possible viewpoints
d. From the project manager's viewpoin
Termination by addition occurs when:
Select one:
a. The project is so successful that it becomes institutionalized.
b. Scope creep adds too many activities to the project that prevent it from being completed on time or within budget.
c. A new project is added to the organization and it commands all of the resources for the original project.
d. New members join the project team once the project has begun and their skills are insufficient to successfully complete the project.