Question: *Please answer within 30mins* Calculate the total project duration from the Activity on Arrow network diagram below (all timings are in days). -EET Activity ID

*Please answer within 30mins* Calculate the total

*Please answer within 30mins*

Calculate the total project duration from the Activity on Arrow network diagram below (all timings are in days). -EET Activity ID d Event ID 18 2 19 SLET 16 Expected Time 18 d 2 un 16 i e 18 10 0 b 20 f 1 3 0 20 14 e 10 18 10 h 4 12 O 41 days O 43 days 34 days O 38 days