Question: please asap Listed in the below table are the tasks and times for a product development project. Activity Predecessor activities Optimistic time, Most likely time,

please asap
Listed in the below table are the tasks and times for a product development project. Activity Predecessor activities Optimistic time, Most likely time, Pessimistic time, weeks weeks weeks A 10 12 14 B 12 21 36 C A 12 13.5 18 D B 16 24 38 E C 12 18 24 F. 2 6 10 Finish DF Expected time in weeks. variance of the expected time in square weeks, and probability that this project is completed in a year are (mark the closest choice): 47, 2.236, 76.2% 47.5,81,499 50.2.236.70.4% 0 50.5. 81.4%Step by Step Solution
There are 3 Steps involved in it