Question: Please calculate the schedule variance given the following information: Earned Value (EV) = 100; Planned Value (PV) = 80 1) -20 2) 100 3) 20
Please calculate the schedule variance given the following information: Earned Value (EV) = 100; Planned Value (PV) = 80
1) -20
2) 100
3) 20
4) 80