Question: please circle answer Given the following network: a) Find the earliest time the project will be completed. b) Find the critical path.. c) If activity

please circle answer
please circle answer Given the following network:
Given the following network: a) Find the earliest time the project will be completed. b) Find the critical path.. c) If activity C is delayed by 4 days, find the completion time of the entire project Activity t E G A B D E F G 5 10 12 8 9 12 7 C B F H H 9