Question: PLEASE COMPLETE WORK IN EXCEL SPREADSHEET ONLY. SHOW ALL FORMULAS/FUNCTIONS TO SHOW ANSWERS (SCREENSHOTS) AND EXPLAIN TO ME HOW YOU GOT THE ANSWER. All WORK
PLEASE COMPLETE WORK IN EXCEL SPREADSHEET ONLY. SHOW ALL FORMULAS/FUNCTIONS TO SHOW ANSWERS (SCREENSHOTS) AND EXPLAIN TO ME HOW YOU GOT THE ANSWER. All WORK SHOULD BE IN EXCEL. SCREENSHOT A PICTURE OF ANSWERS THEN A SCREENSHOT OF FORMULAS IN EXCEL
The data below represent time study observations for an assembly operation. Assume a 7% allowance factor. What is the normal time for each element? What is the standard time for the assembly operation?
| Observations (times in minutes) | ||||||
| Element | Performance Rating | 1 | 2 | 3 | 4 | 5 |
| 1 | 100% | 1.5 | 1.6 | 1.4 | 1.5 | 1.5 |
| 2 | 90% | 2.3 | 2.2 | 2.1 | 2.2 | 2.4 |
| 3 | 115% | 1.7 | 1.9 | 1.9 | 1.4 | 1.6 |
| 4 | 100% | 3.5 | 3.6 | 3.6 | 3.6 | 3.2 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts