Question: please convert this work breakdown structure to a network diagram. You only need to do it for phase 1 and please show the critical path,

please convert this work breakdown structure to a network diagram. You only need to do it for phase 1 and please show the critical path, forward and back pass, and float.
please convert this work breakdown structure to a
please convert this work breakdown structure to a
1. Start-up
1.1 Prototype
1.1.1 Develop first prototype
1.1.2 Pitch design to investors
1.2 Financial aid
1.2.1 Obtain financial aid from investors
1.3 Staff
1.3.1 Hire employees
1.3.2 Training program for all employees.
2. Expansion
2.1 Deliveries
2.1.1 Load small packages onto delivery vehicles
2.1.2 Begin small deliveries
2.2 Storage
2.2.1 Packaging finished goods
2.2.2 Packaged products
2.3 Insurance
2.3.1 Take out insurance on vehicles
3. Mass production
3.1 re-order
3.1.1 stock noted at 20% capacity
3.1.2 suppliers are contacted
3.2 more space
3.2.1 obtain more space for stock storage
3.2.2 pay rent
3.3 mass deliveries
3.3.1 purchase 3 more delivery vehicles
3.3.2 deliver finished products in bulk
this is what each point is, incase its not clear in the pictures.
1.3.2 Work Breakdown Structure Power banks and inverters Pogistics system 1 Soup 2 Exporsion 3 Mos production 12 Francia oid Polope 1.350 21 Delvis 22roge 23 ore 3.1 te-order 32 More 13.1 employees 321 Obio 211 Lood mol package oro delivery Puchares 22.1 Package the frihed pood 23.11 Ou nonce poleon 3.1.1 Sock oled of 205 Copy Ooo froncidid for sorge 132 og tege progonte 212 Supple be conced 221 Packaged produch po ge 13 maling deliveries 332 hed product buto Figure 3: Work Breakdown Structure diagram lish (South Africa) Focus 20 (@ 8 tv MacBook Pro Phase Phase 1: Start-up phase Due date 21" November 2020 Deliverable Develop the prototype and pitch the product to relevant investors. Obtain financial aid from investors. 20th December 2020 Development of first product => Purchase equipment = Training program for employees. = Outgoing deliveries. Financial aid 21 December 2020 30th December 2020 15 January 2021 New employees will be required to undergo a training program to determine their skill levels. Purchase all the necessary equipment in order to manufacture a few devices. Request, from our supplier a six month supply of equipment. Deliverable Outgoing deliveries will become more frequent. Packaged products need to be stored in the warehouse ready for delivery. Take out insurance policies on delivery vehicles and inventory Phase Phase 2: Expansion of production phase Due date 15th January 2021 31 March 2021 1" May 2021 Increase the number of deliveries. Storage of goods. Obtain insurance on delivery vehicles. Phase Phase 3: Mass production phase Deliverable Due date 19 October 2021 Move storage facility to warehouse. Re-order materials when stock is at 20% capacity 1" January 2022 Re-locate storage facility of finished products, - Start mass deliveries to wholesalers. > Acquire more delivery vehicles > Start re-ordering Purchase 3 more delivery vehicles. 30 April 2022 1 June 2022 Deliver finished products in bulk to wholesalers. (South Africa) Focus 20 tv

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!