Question: Please crash the network Activity Information: Activity Predecessors Duration Crash Duration Crash Cost / Unit A - 2 1 8 0 0 B - 3

Please crash the network
Activity Information:
Activity Predecessors Duration Crash Duration Crash Cost/Unit
A -21800
B -32500
C -42400
D A 74500
E B, D, C 63900
F B, C 53100
G D, E 97200
H F 84150
I G, H 10800
 Please crash the network Activity Information: Activity Predecessors Duration Crash Duration