Question: Please create a Cost estimate for a project with the requirements: Purpose: Instructional facility to house a Maker-space, Industrial/Mechanical classrooms and shop Structure: Steel-frame, open-span
Please create a Cost estimate for a project with the requirements:
Purpose: Instructional facility to house a Maker-space, Industrial/Mechanical classrooms and shop
Structure: Steel-frame, open-span construction with framed classrooms and other rooms contained within, two external personnel doors, two 12' x 12' overhead doors. Structure to be thermally insulated and climate controlled.
Contents: Two ~750 sq. ft. classrooms, three ~100 sq. ft. faculty offices, two ~100 sq. ft. restrooms (ladies & mens), two ~150 sq. ft. secure storage rooms, ~6800 sq. ft. open space for Maker-space and shop
.Location/Orientation: Structure will be erected as an independent structure adjacent to existing facility and connected via an enclosed breezeway, approximately 10' wide by 50' long (to be included in project).
Time Frame: Physical construction may commence on June 1 and the facility must be ready to occupy by November 30 in order to be placed in service for the second half of the academic year beginning in January. (You have a six-month construction window.)
That also has a schedule as follows.
[Start] --> [Excavation and foundation] --> [Steel-Frame construction] --> [Roofing and insulation] -->
[Climate control setup].
[Steel-Frame Construction] --> [Classroom framing] --> [overhead door installation] --> [Breezeway construction].
1. Excavation and foundation: 30 days
2. Steel-Frame construction: 60 days.
3. Classroom framing: 30 days.
4. Overhead door installation: 10 days.
5. Secure storage rooms: 10 days.
6. Restrooms: 20 days ( 10 days).
7. Climate control setup: 10 days.
8. Roofing and insulation: 15 days.
9. Breezeway construction: 20 days.
10. Interior finishing: 45 days.
11. Electrical installations: 20 days.
12. Plumbing installations: 20 days
13. HVAC installations: 30 days.
14. Flooring and painting: 30 days.
15. Final inspections: 10 days.
16. Move-in and setup: 15 days.