Question: Please create a Microsoft Word document that answers the following questions. For this assignment, please just answer each question. Please calculate the Expected Monetary Value?
Please create a Microsoft Word document that answers the following questions. For this assignment, please just answer each question.
- Please calculate the Expected Monetary Value? (5 points each = 25 Points Total)
- Project A: Probability of Risk: 10% | Impact $20,000
- Project B: Probability of Risk: 30% | Impact $45,000
- Project C: Probability of Risk: 28% | Impact $18,000
- Project D: Probability of Risk: 100% | Impact $97,500
- Project E: Probability of Risk: 5% | Impact $10,000
- For each of the following, identify the Response Response Strategy and explain why you would select that strategy? (10 points each = 50 Points Total).
- Remove a work package or activity from the project.
- Assign a team member to visit the seller's manufacturing facilities frequently to learn about a problem with delivery as early as possible
- Move a work package to a date when a more experienced resource is available to be assigned to the project.
- Begin negotiation for the equipment earlier than planned so as to secure a lower price.
- Outsource a work package so as to gain an opportunity.
- Notify management that there could be a cost increase if a risk occurs because no action is being taken to prevent the risk.
- Remove a troublesome resource from the project.
- Provide a team member who has limited experience with additional training.
- Train the team on conflict resolution strategies.
- Outsource difficult work to a more experienced company.
- Find an example of a company that took a big risk on an IT project and fail. What happened? Why did it fail? (25 points)
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock