Question: Please Create a proposed Operator Balance Chart In one company, production time available per day is 480 minutes and 40 units are required per day.

Please Create a proposed Operator Balance Chart Please Create a proposed Operator Balance Chart
In one company, production time available per day is 480 minutes and 40 units are required per day. The data is shown below for nine tasks. TASK TIME PRIORITY OF TASK A B C D E F G H I TOTAL TIME 10 11 5 4 12 3 7 11 3 66 A B B. A C, D F E G, H