Question: PLEASE DEFINE SETS, PARAMETERS,VARIABLES, OBJECTIVE FUNCTION, AND CONSTRAINTS FOR FULL ANSWER A company has four machines and four jobs to be completed. Each machine must

PLEASE DEFINE SETS, PARAMETERS,VARIABLES, OBJECTIVE FUNCTION, AND CONSTRAINTS FOR FULL ANSWER
A company has four machines and four jobs to be completed. Each machine must be assigned to complete one job. The time required to set up each machine for completing each job is shown in following table. The company wants to minimize the total setup time needed to complete the four jobs. Setup Times Machine Job 4 - Job 1 14 - 2 Time (Hours) Job 2 Job 3 5 8 12 6 8 3 4 6 10 Use linear programming to solve thisStep by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts