Question: Please do Activity/ES/EF for A,B,C and D Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like

Please do Activity/ES/EF for A,B,C and D
Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Immediate Predecessor(s) Time Activity (weeks) 5 B 6 3 D 3 Time Activity (weeks) E 3 F 6 G 11 H 6 Immediate Predecessor(s) B B C, E DF A A Dave's earliest start (ES) and earliest finish (EF) are: ES EF Activity A 5Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock