Question: *PLEASE DO NOT COPY ANSWER FROM ANOTHER POST. NUMBERS ARE DIFFERENT!!! 2. A student has developed a project and is interested in accelerating the schedule.
*PLEASE DO NOT COPY ANSWER FROM ANOTHER POST. NUMBERS ARE DIFFERENT!!!
2. A student has developed a project and is interested in accelerating the schedule. Below network diagram (Activity on Arrow) and table show all information needed. Partial crashing is available. Show your work for crashing. b C Present Duration Cost 3 $100 4 $50 $250 $100 $100 $300 5 3 6 7 Accelerated Duration Cost $200 $S100 2 3 4 $350 cannot accelerate $150 $600 5 5 a) Without any crashing (acceleration), how long is the project expected to take? b) Crash the project by maximum available time. What activities should we crash? c) What is the total additional cost for maximum crash