Question: Present Accelerated Duration Cost Duration Cost a 3 $100 2 $200 b 4 $ 50 3 $100 c 5 $250 4 $350 d 3 $100
|
2. A student has developed a project and is interested in accelerating the schedule . Below network diagram (Activity on Arrow) and table show all information needed. Partial crashing is available. Show your work for crashing.
- Without any crashing (acceleration), how long is the project expected to take?
- Crash the project by maximum available time. What activities should we crash?
- What is the total additional cost for maximum crash?