Question: Please do not copy-paste answers given by others. Problem 4 Assume you have a project with ten activities labeled A through J. Derive the earliest
Please do not copy-paste answers given by others.
Problem 4
Assume you have a project with ten activities labeled A through J. Derive the earliest expected completion time (TE), latest expected completion time (TL), and slack for each of the tasks (begin at time = 0).
A) Complete the missing values in the table
B) Draw a network diagram and show the critical path
| Activity | Preceding event | Duration | TE | TL | Slack | Critical Path? |
|---|---|---|---|---|---|---|
| A | 4 | |||||
| B | A | 5 | ||||
| C | A | 6 | ||||
| D | A | 7 | ||||
| E | A, D | 6 | ||||
| F | C, E | 5 | ||||
| G | D, E | 4 | ||||
| H | E | 3 | ||||
| I | F, G | 4 | ||||
| J | H, I | 5 |