Question: Please do not copy-paste answers given by others. Problem 4 Assume you have a project with ten activities labeled A through J. Derive the earliest

Please do not copy-paste answers given by others.

Problem 4

Assume you have a project with ten activities labeled A through J. Derive the earliest expected completion time (TE), latest expected completion time (TL), and slack for each of the tasks (begin at time = 0).

A) Complete the missing values in the table

B) Draw a network diagram and show the critical path

Activity Preceding event Duration TE TL Slack Critical Path?
A 4
B A 5
C A 6
D A 7
E A, D 6
F C, E 5
G D, E 4
H E 3
I F, G 4
J H, I 5