Question: Problem 4 Assume you have a project with ten activities labeled A through J. Derive the earliest expected completion time (TE), latest expected completion time

Problem 4 Assume you have a project with ten

Problem 4 Assume you have a project with ten activities labeled A through J. Derive the earliest expected completion time (TE), latest expected completion time (TL), and slack for each of the tasks (begin at time - 0). A) Complete the missing values in the table B) Draw a network diagram and show the critical path Activity Preceding event Duration TE TL Slack Critical Path? A 4 B A 5 A 6 ID A 7 E 6 F 5 G 4 AD ICE DE E IEG HI IH 3 4 0 5