Question: PLEASE DO NOT USE COMMA ( S ) ON YOUR ANSWER!!! A proposed embankment fill requires 8 4 0 0 f t 3 of compacted
PLEASE DO NOT USE COMMAS ON YOUR ANSWER!!!
A proposed embankment fill requires of compacted soil. The void ratio of the compacted fill is specified as Four borrow pits are available as below, which list the respective void ratios of the soil and the cost per cubic feet for moving the soil to the proposed construction site. Make the necessary calculations to determine the total cost for each pit. Assume the specific gravity of soil solids, Gs to be the same at all pits.
Calculate the volume of solid Vs
Borrow Pit A: void ratio and the unit cost $
Calculate the total cost to pay to Pit
Borrow Pit B: void ratio and the unit cost $
Calculate the total cost to pay to Pit
Borrow Pit C: void ratio and the unit cost $
Calculate the total cost to pay to Pit
Borrow Pit D: void ratio and the unit cost $
Calculate the total cost to pay to Pit
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock