Question: please don't solve it with paper 3. Draw the PERT Diagram related to the following tasks Task Duration precedence A 3 B 4 A 2
please don't solve it with paper

3. Draw the PERT Diagram related to the following tasks Task Duration precedence A 3 B 4 A 2 A D 5 B E 1 F 2 G 4 DE H 3 F G 4. Draw the GANTT Diagram related to previous tasks 5. Identify the critical path after calculating the slack time for each task