Question: PLEASE DON'T TAKE THE ANSWER FROM ANOTHER QUESTION THE NUMBERS ARE DIFFERENT!!!!! Three activities are candidates for crashing on a project network for a large

PLEASE DON'T TAKE THE ANSWER FROM ANOTHER QUESTION THE NUMBERS ARE DIFFERENT!!!!!

PLEASE DON'T TAKE THE ANSWER FROM ANOTHER

Three activities are candidates for crashing on a project network for a large computer installation (all are, of course, critical). Activity details are in the following table: Immediate Predecessor(s) Activity A Normal Time Crash Time Normal (days) (days) Cost 7 6 $6,000 4 2 $1,400 11 9 $4,200 Total Cost with Crashing $6,600 $3,300 $6,200 B A B a) Activity that should be crashed first to reduce the project duration by 1 day is A b) Activity that should be crashed next to reduce the project duration by one additional day is B c) Total cost of crashing the project by 2 days = $ (Enter your response as an integer.)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!