Question: please draw the activity diagram . as per my calculation the project needs 8 weeks to finish I know that after calculated the critical path

please draw the activity diagram . as per my

please draw the activity diagram . as per my calculation the project needs 8 weeks to finish I know that after calculated the critical path but I want you to consider 6 weeks in your calculation ,neglect the remaining 2 weeks .

kholol Sv=2? CPI =?? SPIS?? 6 week ETC=?? CV=?? EAC=?? AC actual Cost duration Budget activity Constate decessors 2 300 400 a 100 b 3 200 2 250 Zou loo C d 5 Goo 20 400 20 4 400 bie e

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!