Question: Please draw the network below. Thats all. On paper. For the small project shown below, perform the CPM calculations to answer the following: a. The
Please draw the network below. Thats all. On paper. 
For the small project shown below, perform the CPM calculations to answer the following: a. The early start (ES) for Activity H is day: b. The late start (LS) for Activity E is day: c. The total float (TF) for Activity J= day(s) and for Activity B= day(s) d. The lag time between Activity E and Activity G= day(s) e. The free float (FF) for Activity A= day(s) and for Activity B= day(s) f. [Bonus 5 points] If Activity E is delayed by 3 days, then Activity I will be delayed by day(s) g. Show the critical path(s) on the network