Question: Please draw this into a critical path diagram. This is different from a previous question on here as it goes all the way til S
Please draw this into a critical path diagram. This is different from a previous question on here as it goes all the way til S and has more tasks/ different predecessors.
| CPM Project Management | |||
| Build A Home | |||
| (days) | |||
| Activity | Description | Predecessors | Time |
| A | Develop Project Plans | 75 | |
| B | Clear Site | A | 5 |
| C | Excavation | B | 3 |
| D | Footings | C | 3 |
| E | Foundation | C | 3 |
| F | Curing | D,E | 7 |
| G | Temporary Power | D,E | 1 |
| H | Framing/Rebar | F | 37 |
| I | Set Roof | H | 2 |
| J | Exterior Walls | J | 2 |
| K | Sheathing | H,J | 4 |
| L | Install Roofing | K | 3 |
| M | Pre-Wiring | J,L,K | 7 |
| N | MEP Inspections | M | 1 |
| O | Drywall/Texture | H,I,K,L,M | 6 |
| P | Cabinet/Doors/Interior Paint | J,K,C | 4 |
| Q | Trim/Molding | P | 1 |
| R | Plumber/Electrician/HVAC/Utilities | O | 7 |
| S | Certificate of Occupancy | N,R | 7 |
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock