Question: please explain 1 and 2 Problem 2: An operation in a company has 20% scrap rate. As a result 800 units are produced in a

please explain 1 and 2
Problem 2: An operation in a company has 20% scrap rate. As a result 800 units are produced in a ten-hour day. The units are produced by 4 workers who use 2 kilos of raw materials per unit. Workers are paid 5 Omani Rials per hour; raw material cost is 500 baiza per kilo. The overhead cost is 60 Omani Rials. 1. Calculate the labor productivity (per worker, per labor hour, per Rial) 2. Calculate the overall productivity (labor +raw material + overhead)Step by Step Solution