Question: please explain and show work. d has no predecessor as you can see in the table. Given the project within the table below, calculate the


please explain and show work. d has no predecessor as you can see in the table.
Given the project within the table below, calculate the following: Duration Immediate Activity (hours) Predecessors | 4 B 3 IC 8 |A, B D 7 E 2 B, C F 3 D, E G 7 F a. What is the project length? 24 hours b. What activities are on the critical path? A, C, E, F, G c. How much slack in in activity B? 1 hour d. What is the Late Start / Late Finish for activity D? 0 hours and 7 hours f. What if activity D was delayed by 8 hours (now taking 15 hours), what impact would it have on the overall project? It would have no impact - theStep by Step Solution