Question: Please explain in detail. the answer isnt S btw... Net present value Lepton Industries has three potential projects, all with an initial cost of $1,600,000
Net present value Lepton Industries has three potential projects, all with an initial cost of $1,600,000 The capital budget for the year will allow Lepton to accept only one of the three projects Given the discount rate and the future cash flow of each project in the following table B determine which project Lepton should accept Which project should Lepton accept? (Select the best response ) O A Project R OB Project OC. None of the projects D. Projects Data table (Click on the following icon in order to copy its contents into a spreadsheet) Cash Flow Project a Project R Projects Year 1 $400,000 $500,000 $900,000 Year 2 $400,000 $500,000 $700.000 Year 3 $400.000 $500,000 $500,000 Year 4 $400,000 $500,000 $300,000 Year 5 $400,000 $500,000 $100,000 Discount rate 10% 11% 17%