Question: Please find below the question, and I need full explanation on the 3.1 part, where you need to seperate the answers as follow: - Expected
Please find below the question, and I need full explanation on the 3.1 part, where you need to seperate the answers as follow:
- Expected activity duration for each of the activities
- A project network (Activity on Node)
- Complete the forward and backward pass,
- Compute the activity slack
- Identity the critical path.
I shall be grateful if you could prepare a full new answer as i saw the answer for this question but it seems to be erroned.
Thanking you beforehand.

QUESTION 3 (20) Your company has signed a contract to build a 500 bed hospital to help ease the pressure on local hospitals during the coronavirus outbreak. You will receive a R500 000 bonus for completing the project within 20 weeks. The contract also contains a penalty clause in which you will lose R70 000 for each week the project takes longer than 20 weeks. The table below shows the project activities. Activity Description Predecessor Optimistic Most Probable Pessimistic A B D E F G H Pour Foundation None Erect Frame A Roof B Windows B Doors B Electrical B Rough Frame C,D,E,F Door Opener E,F Paint GH Cleanup I 1 2 3 1 1 1 2 1 2 1 3 4 4 1 1 3 2 1 2 1 4 6 5 1 1 5 3 I J 1 3 3 3.1. Calculate the expected activity duration for each of the activities and draw a project network (Activity on Node) given the information below. Complete the forward and backward pass, compute the activity slack, and identify the critical path. *2.45 days/weeks is rounded off to 3 days/weeks 3.2. Do you expect to receive a bonus or a penalty on this project?||