Question: Please fully Draw out the project network to show the ES,LS,EF,LF and Slack, Critical Path in the drawing. 2. A project network is shown below.
Please fully Draw out the project network to show the ES,LS,EF,LF and Slack, Critical Path in the drawing.
2. A project network is shown below. Use a forward and a backward pass to determine the critical path, and then fill out the table below. Activity times are in weeks