Question: PLEASE GIVE AN ORIGINAL ANSWER. IVE VIEWED ALL OTHER ALREADY POSTED The G&E Company is preparing a bid to build the new 47,000-seat Shoreline baseball

PLEASE GIVE AN ORIGINAL ANSWER. IVE VIEWED ALL OTHER ALREADY POSTED

The G&E Company is preparing a bid to build the new 47,000-seat Shoreline baseball stadium. The construction must start on July 3, 2017, and be completed in time for the start of the 2020 season. A penalty clause of $250,000 per day of delay beyond April 3 is written into the contract.

Percival Young, the president of the company, expressed optimism at obtaining the contract and revealed that the company could net as much as $3 million on the project. He also said if they were successful, the prospects of future projects are bright since there is a projected renaissance in building classic ball parks with modern luxury boxes.

ASSIGNMENT

Given the information provided in Table construct a network schedule for the sta- dium project and answer the following questions:

  1. WilltheprojectbeabletobecompletedbytheApril3deadline?Howlongwillittake?
  2. What is the critical path for the project?
  3. Based on the schedule would you recommend that G&E pursue this contact? Why?
  4. Include a one-page Gantt chart for the stadium schedule.

For purposes of this case assume the following:

  1. The following holidays are observed: January 1, Martin Luther King Day (third Monday in January), Memorial Day (last Monday in May), July 4th, Labor Day (first Monday in September), Thanksgiving Day (4th Thursday in November), December 25 and 26.
  2. If a holiday falls on a Saturday then Friday will be given as an extra day off, and if it falls on a Sunday then Monday will be given as a day off.
  3. The construction crew work Monday through Friday.

PLEASE GIVE AN ORIGINAL ANSWER. IVE VIEWED ALL

ID Duration Predecessor(s) . Activity Baseball Stadium Clear stadium site Demolish building Set up construction site Drive support piling Pour lower concrete bowl Pour main concourse Install playing field Construct upper steel bowl Install seats Build luxury boxes Install jumbotron Stadium infrastructure Construct steel canopy Light installation Build roof supports Construct roof Install roof tracks Install roof Inspection 70 days 30 days 70 days 120 days 120 days 120 days 90 days 120 days 140 days 90 days 30 days 120 days 75 days 30 days 90 days 180 days 90 days 90 days 20 days | 14 15 16 17 18 19 20 9 9 9 10 10 4 16 14 17, 18 8, 11, 13, 15, 19

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!