Question: please give me a good answer for number two. I just need the answer for number two. Please give me a good answer that is

please give me a good answer for number two. I just need the answer for number two. Please give me a good answer that is not already on chegg thank you I will give a good review
please give me a good answer for number two. I just need
the answer for number two. Please give me a good answer that

The Port of Endover operates six berths and 12 cranes for loading and unloading freight containers from ships, organized into two areas known as the north terminal and the south terminal. The Port of Endover's north terminal contains two of the ship berths and four of the cranes, which worked together almost continuously last week, handling (loading or unloading) a total of 14,599 freight containers during 151 hours of operation. Similarly, the eight cranes of the larger south terminal operated together over 160 hours last week, collectively handling 29,753 containers. Questions overall per crane productivity of the Port of Endover last week? 2. What was the "per hour of operation" productivity of the north terminal last week? What was the "per hour of operation" productivity of the south terminal last week? 3. The four cranes of the north terminal require one crane operator each, plus two

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

To calculate the per hour of operation productivity for each terminal well d... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!