A project has 7 activities P, Q, R, S, T, U, and V. Activity times and precedence relations are given below:
| Activity | Immediate predecessor(s) | Activity time (days) |
| P | - | 6 |
| Q | - | 7 |
| R | - | 3 |
| S | P, Q | 9 |
| T | Q,R | 5 |
| U | S,T | 2 |
| V | T | 7 |
In the box given below, write down
-
the earliest finish time of Q
-
the earliest finish time of S
-
the earliest finish time of T
-
the earliest finish time of U
-
the latest start time of Q
-
the latest start time of R
-
the latest start time of S
-
the latest start time of T