Question: Please handwrite ur answer and explain BUT DON'T COPY FROM ONLINE SOURCES OR OTHER CHEGG ANSWERS PLZ:(. I WILL THUMBS UP!!!!!!! A project has 7

Please handwrite ur answer and explain BUT DON'T COPY FROM ONLINE SOURCES OR OTHER CHEGG ANSWERS PLZ:(. I WILL THUMBS UP!!!!!!!

A project has 7 activities P, Q, R, S, T, U, and V. Activity times and precedence relations are given below:

Activity Immediate predecessor(s) Activity time (days)
P - 6
Q - 7
R - 3
S P, Q 9
T Q,R 5
U S,T 2
V T 7

In the box given below, write down

  1. the earliest finish time of Q

  2. the earliest finish time of S

  3. the earliest finish time of T

  4. the earliest finish time of U

  5. the latest start time of Q

  6. the latest start time of R

  7. the latest start time of S

  8. the latest start time of T

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!