A project has 7 activities P, Q, R, S, T, U, and V. Three time estimates (optimistic, most-likely, pessimistic) are used for each activity.
Write down your answers to all parts of the question in the box given below. Give your answer to 3 decimal places. (Note (a) has of 2 parts and (b) has of 3 parts)
-
For activity Q, these time estimates are as follows: optimistic time = 9, most-likely time = 16, pessimistic time = 23. Write down
-
the average activity time for Q
-
the variance of activity time for Q.
-
-
The critical path of this project has a mean project time of 39 days and a standard deviation of 8 days. Assume project completion time is normally distributed.
-
Find the probability that the project will be completed in 50 days.
-
Find the probability that the project will take more than 25 days.
-
We want to set a deadline for this project completion. If the probability of meeting this set deadline is 0.91, what will be the deadline for this project.
-
Step by Step Solution
There are 3 Steps involved in it