Question: PLEASE HELP A&B , D ! ! C ANSWER = 1 , 6 1 1 . 7 8 mm ! ! As part of a

PLEASE HELP A&B,D!! C ANSWER=1,611.78mm!!
As part of a construction project, a 16 meter-thick layer of clay is to be loaded with a temporary 5-meter thick sand layer (see figure below). The figure shows the water-table location, soil unit weights, and the compression-curve properties for the clay. Assume that the sand layer remains dry. The clay has an initial OCR of 1.5(which is constant throughout layer).
a. Calculate the ultimate settlement that will occur under these conditions (at the surface of the sand)(in units of mm).
b. How much will the clay layer heave when the 5-meter sand layer loading is removed (in units of mm?
c. If instead a 10-meter thick sand layer was applied, what would the resulting ultimate settlement be under these conditions (at the surface of the sand)(in units of mm)? ANSWER=1,611.78mm
d. Is your answer from part c twice your result from part a? Does this make sense? Why or why not?
PLEASE HELP A&B , D ! ! C ANSWER = 1 , 6 1 1 . 7

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!