Question: PLEASE HELP!!!!! B, C Activity Duration (weeks) Precedes Crash Cost/Week A (start) 3 $380 B 2 E $110 5 F $220 E 1 F $160

PLEASE HELP!!!!!
PLEASE HELP!!!!! B, C Activity Duration (weeks)
B, C Activity Duration (weeks) Precedes Crash Cost/Week A (start) 3 $380 B 2 E $110 5 F $220 E 1 F $160 F (end) 2 $420 Suppose that Rafay is only given 7 weeks (instead of 10) to complete the project. By how many weeks should each activity be crashed in order to meet the deadline? Assume that you can crash an activity down to o weeks duration. Activity A B Each Activity Should be Reduced BY (weeks) week(s) week(s) week(s) week(s) week(s) E F What is the total crashing cost? $(Enter your response as a whole number.)