Question: Please also answer question (b) b) What is the total crashing cost? $____ ( Enter your response as a whole number. ) 8. The following

Please also answer question (b)
b) What is the total crashing cost? $____ (Enter your response as a whole number.)
8. The following is a table of activities associated with a project at Rafax Ishfaq's software firm in Chicago, their durations, what activities each must precede and the crash cost to reduce duration per week: Activity Duration (weeks) Precedes Crash Cost/Week A (start) 3 B, C $380 B 2 D $130 5 E $240 D 2 E $140 E (end) 2 $400 Suppose that Rafax is only given 8 weeks instead of 10) to complete the project. a) [2 pts] By how many weeks should each activity be crashed in order to meet the deadline? Assume that you can crash an activity down to 0 weeks durationStep by Step Solution